Ready to start: false
Assignee:
Project: Kokonut Seeds
Category: Infrastructure
Phase: Land Preparation
Budget: $ 2137.28
Start: 2024-07-24
Duration: days
Until deadline: -56 days
Estimated end date: 2024-07-24
Actual end date:
Days overdue:
Name | Availble |
---|---|
Date | Description |
---|---|
2024-09-09T23:26:59.272599Z | We completed the construction, installation, and setup of the farm irrigation system; we ran a test, and it was a success, we have the system up and running across the 7 campuses of the farm. |
2024-09-04T23:36:35.484108Z | The team continues to work connecting the water lines and tubes for the system to be fully completed. |
2024-09-03T23:09:38.041810Z | The irrigation system for the farm is in the final installation steps, today some rain didn't allow the contractors to continue with the work. Hopefully, we can complete it within 24â48 hours as the Planting Phase is delayed because of these minimal delays, but as seedlings are secured, we will be up and running in no time. |
2024-08-27T23:36:41.033325Z | The work for the irrigation system began with the Preparation of the land for the Water Tubes that will cover the plots of land. |
2024-08-26T23:11:31.225280Z | We've made the first payment for the irrigation system and our engineer is gathering the components to install the system; the work we will start Tuesday 27. |
2024-08-22T23:13:48.906503Z | The Irrigation System engineer went to the project and made a full survey of the land to polish the initial quote to fit it within our budget. |
2024-07-24T23:54:02.232879Z | We began the construction of the water reservoir; step one was to make the hole. The next step is to build the structure. |