T-Kokonut Seeds-31: Water Pumping System (In progress)

 

ℹ️ Information

Ready to start: true

Assignee:

Project: Kokonut Seeds

Category: Infrastructure

Phase:

Budget: $ 2030.46

⏱️ Timing

Start:

Duration: days

Until deadline: days

Estimated end date:

Actual end date:

Days overdue:

🏗️ Required equipment

NameAvailble
No items have been found.

🎬 Task actions

DateDescription
2024-09-04T23:40:10.510428Z
We acquired the water pump and the accessories needed, it was the final piece of the Farm Water System.
2024-09-03T23:07:10.621172Z
The Water Reservoir has been completed, and it is receiving water from one of the sources we secured for the farm
2024-08-27T23:38:23.895976Z
We finalized the construction of the Water Reservoir; we will reinforce the outer structure now for the durability of the investment.
2024-08-26T23:09:52.319071Z
We're putting the final touches to the construction of the water reservoir, it should be completed by Wednesday 28.
2024-08-22T23:11:27.626712Z
The construction of the water reservoir is still going as planned, it is almost completed, and as of today, it is 70% done.
2024-08-14T23:05:24.925626Z
We're finalizing the steel structure for the water reservoir in preparation for the next of construction.
2024-08-06T23:31:41.534945Z
We detect a mistake in the measurements for the water reservoir, so we had to hire someone to finish the job manually
2024-08-02T23:24:40.505249Z
We began to receive the construction materials for the Water Reservoir and the Lead Engineer was doing a final scout to the hole.
2024-07-31T01:39:11.225603Z
We received the quote from the Hardware Store and from the team that is going to perform the construction of the water reservoir, now we will proceed to purchase the construction materials
2024-07-29T23:11:08.605280Z
We finalized the hole for the water reservoir, next step is to take measurements and quote the construction job.
2024-07-27T21:08:25.716592Z
Today we will finalize the hole to build the water reservoir for the farm