Ready to start: true
Assignee:
Project: Kokonut Adelphi
Category: Operations
Phase:
Budget: $
Start:
Duration: 365 days
Until deadline: days
Estimated end date:
Actual end date:
Days overdue:
| Name | Quantity |
|---|---|
| Activity Name | Outputs | Start Date | Activity End date |
|---|---|---|---|
| Name | Category | Date | Amount | Expense Status | Personas Impactadas |
|---|---|---|---|---|---|
Wood & Utility Poles Purchase | Materials | 2025-05-10 | $188.81 | Audited | 4 |
Completion of House Construction | Infrastructure | 2025-05-14 | $1361.93 | Audited | 16 |
Key Copies (3 Sets) | Various | 2025-05-26 | $11.88 | Paid | 1 |