T-Kokonut Adelphi-193: Staff Payroll (Annual) (In progress)

 

ℹ️ Information

⏱️ Timing

🏗️ Required equipment

NameQuantity
No items have been found.

🎬 Task Activities

Activity NameOutputsStart DateActivity End date

Single-Phase Transformer Installation (25 kVA)

Farm Electrical Grid & Security Lighting Installation

2025-05-10

2025-05-10

Post Hole Installation (Power Line Support Poles)

2025-05-13

2025-06-13

Power Line Improvements – Phase 1 (Fuse Installation / Cut-Out)

Strengthened Electrical Infrastructure & System Stabilization

2025-05-26

2025-06-26

Power Line Improvements – Phase 2 (External Electrical Wiring Completion)

Strengthened Electrical Infrastructure & System Stabilization

2025-05-29

2025-05-30

Power Line Improvements – Phase 3 (Grid Stabilization & Security Systems)

4G Security Camera Installation for Farm Monitoring,Strengthened Electrical Infrastructure & System Stabilization

2025-06-02

2025-06-02

Power Line Improvements – Phase 4 (Insulation & Line Splicing)

Strengthened Electrical Infrastructure & System Stabilization

2025-06-08

2025-06-08

🎬 Task Expenses

NameCategoryDateAmountExpense StatusPersonas Impactadas

25 kVA Single-Phase Transformer Purchase

Infrastructure

2025-05-07

$1003.74

Audited

8

Electrical Installation Services

Infrastructure

2025-05-10

$578.33

Audited

4

Post Hole Excavation & Pole Installation Labor

Labor

2025-05-13

$27.22

Audited

2

Power Line Improvements

Maintenance

2025-05-26

$420.13

Paid

2

Field Operations Logistics

Logistics

2025-05-31

$61.04

Audited

4