Ready to start: true
Assignee:
Project: Kokonut Adelphi
Category: Operations
Phase:
Budget: $
Start:
Duration: 365 days
Until deadline: days
Estimated end date:
Actual end date:
Days overdue:
| Name | Quantity |
|---|---|
| Activity Name | Outputs | Start Date | Activity End date |
|---|---|---|---|
Single-Phase Transformer Installation (25 kVA) | Farm Electrical Grid & Security Lighting Installation | 2025-05-10 | 2025-05-10 |
Post Hole Installation (Power Line Support Poles) | 2025-05-13 | 2025-06-13 | |
Power Line Improvements – Phase 1 (Fuse Installation / Cut-Out) | Strengthened Electrical Infrastructure & System Stabilization | 2025-05-26 | 2025-06-26 |
Power Line Improvements – Phase 2 (External Electrical Wiring Completion) | Strengthened Electrical Infrastructure & System Stabilization | 2025-05-29 | 2025-05-30 |
Power Line Improvements – Phase 3 (Grid Stabilization & Security Systems) | 4G Security Camera Installation for Farm Monitoring,Strengthened Electrical Infrastructure & System Stabilization | 2025-06-02 | 2025-06-02 |
Power Line Improvements – Phase 4 (Insulation & Line Splicing) | Strengthened Electrical Infrastructure & System Stabilization | 2025-06-08 | 2025-06-08 |
| Name | Category | Date | Amount | Expense Status | Personas Impactadas |
|---|---|---|---|---|---|
25 kVA Single-Phase Transformer Purchase | Infrastructure | 2025-05-07 | $1003.74 | Audited | 8 |
Electrical Installation Services | Infrastructure | 2025-05-10 | $578.33 | Audited | 4 |
Post Hole Excavation & Pole Installation Labor | Labor | 2025-05-13 | $27.22 | Audited | 2 |
Power Line Improvements | Maintenance | 2025-05-26 | $420.13 | Paid | 2 |
Field Operations Logistics | Logistics | 2025-05-31 | $61.04 | Audited | 4 |